Webbing Slings Warning

The tragic death of a worker on the Adelaide desalination plant is a sad reminder of the inherent dangers of synthetic slings.

The accident occurred when a synthetic sling failed.

Any use of synthetic slings must be part of a 'Safe Work Method Statement' that takes into account possible hazards and potential damage to the sling.

The NSW ‘Guide For Rigging’ includes this chapter on synthetic slings:

Inspection

Synthetic slings must be inspected before each use. They must also be inspected at least once every three months. If a sling is subject to severe conditions the inspections should be more frequent. Send each sling for a proof load test at least every 12 months.